Case study - Power station
In November 2001 Procon helped Eskom with their onsite clean up. Here are the details and photographs from the clean-up at this power station:
Product: Transformer Oil
Industry: Power Generation
Client: Eskom
Location: Kendal Power Station
Application: Transformer oil spillage into clarifier and dams
Equipment supplied: Spinifex Mobile Emergency Unit SP4500 unit
Project Summary:
- 20,000 Litres recovered from clarifier in 5 days (24 hour operation).
- 42,000 Litres recovered from dams in 11 days (24 hr operation).
Clarifier
BEFORE :: AFTER

Dams